All streets around the convention center are currently open.

Download past newsletters:

 

The expansion project at a glance.

The $325 million transformation of the Henry B. Gonzalez Convention Center will ensure that San Antonio will have the type of world-class convention facilities that can attract business and travelers to our city for decades to come. When the new facility is open, the oldest portion of the current convention center complex will be demolished and enable Hemisfair Park to realize its vision of creating a vibrant mixed-use area centered on a city park. Read more about the plans and benefits.

To create room for the transformation of the convention center, Market Street will be realigned parallel to Commerce Street, creating better connection to the East Side of San Antonio and direct access to I-37 from downtown.

OxBlue Construction Cameras

October

2012

October 2012 through November 2013

November

2013

November 2013

March

2014

  • Drill Piers and Foundation: Spring 2014 – Winter 2014
  • Concrete Slabs: Summer 2014 – Spring 2015
  • Steel Erection: Spring 2014 – Winter 2014

December

2015

  • December 2015 – New construction completion
  • Exterior Closure: Fall 2014 – Fall 2015
  • Interior Finish Out: Summer 2014 – Winter 2015

April

2016

  • April 2016 – West Wing demo begins 1st quarter 2016
  • West Bldg. Demo:  Spring 2016 – Summer 2016
  • West Bldg. Interior Finish Out:  Spring – Summer 2016

July

2016

  • West Substantial Completion:  July 1, 2016 (contractual)
  •  Final demo & project completion:   July 31, 2016 (contractual)

May

2013

  • Closure of the Commerce Contraflow Lane (April 29, 2013)
  • Widening of Frontage Road and South-Bound Entrance Ramp South of Chavez
  • Installation of Chilled Waterline (Chavez to Bowie)
  • Storm Drain Outfall Along Montana/Crossing Bowie (Intermittent Lane Closures) (5) Retaining Walls Along IH-37
  • Utilities (AT&T, Chilled Waterline, CPS Gas, Time Warner, CPS Underground, etc… )

read more »

December

2014

October, 2012 Design Begins

October 2012 through November 2013

May, 2013 Market Street Realignment Phase 1
  • Closure of the Commerce Contraflow Lane (April 29, 2013)
  • Widening of Frontage Road and South-Bound Entrance Ramp South of Chavez
  • Installation of Chilled Waterline (Chavez to Bowie)
  • Storm Drain Outfall Along Montana/Crossing Bowie (Intermittent Lane Closures) (5) Retaining Walls Along IH-37
  • Utilities (AT&T, Chilled Waterline, CPS Gas, Time Warner, CPS Underground, etc… )

read more »

November, 2013 Main construction starts

November 2013

March, 2014 Spring Construction

Drill Piers and Foundation: Spring 2014 – Winter 2014 Concrete Slabs: Summer 2014 – Spring … read more »

December, 2014 Market Street Completed
December, 2015 Fall 2015 expansion completion

December 2015 – New construction completion Exterior Closure: Fall 2014 – Fall 2015 Interior Finish … read more »

April, 2016 West Wing demo begins

April 2016 – West Wing demo begins 1st quarter 2016 West Bldg. Demo:  Spring 2016 … read more »

July, 2016 Final demo and project completion

West Substantial Completion:  July 1, 2016 (contractual)  Final demo & project completion:   July 31, 2016 … read more »